Kitchen Renovation Timeline Vancouver: Week-by-Week What to Expect

Knowing what happens each week of your kitchen renovation reduces anxiety and helps you plan around construction disruption. Here’s a typical timeline for a mid-range kitchen renovation in Metro Vancouver.

Weeks 1–6: Pre-Construction Phase

Week 1–2: Contract signed, permit application submitted, cabinet order placed (8–12 week lead time begins), tile and fixtures selected and ordered (4–8 week lead time begins). Permit and materials run in parallel — this is critical to avoid a 3-month wait vs. a 6–8 week wait.

Week 3–6: Permit processing at City of Vancouver. VGC project manager confirms all material orders, schedules subtrades (plumber, electrician, tile setter), and coordinates dumpster placement and site protection for demo day.

Week 7: Demo Week

Permit received (or arrives during this week for most straightforward projects). Existing kitchen demolished: cabinets removed, counters removed, tile floor removed, old appliances removed, drywall opened as needed for rough-in access. Demo typically takes 1–2 days. Dumpster hauled.

Week 8: Rough-In

New plumbing supply and drain rough-in (if relocating sink or island plumbing), electrical rough-in (new circuits for refrigerator, dishwasher, range, microwave, under-cabinet lighting), any structural changes (beam installation if wall removed). City rough-in inspections scheduled and completed.

Week 9: Drywall and Prep

New drywall patched and finished where opened, texture matched, primer coat. Floor substrate prepared (cement board, self-leveling compound if needed). Ceiling patched. End of week: kitchen is ready for installation to begin.

Week 10–11: Cabinet and Countertop Installation

Day 1–2: Cabinet delivery and installation (typically 2 days for a full kitchen). Day 3: Plumbing rough-in trim begins (faucet holes templated). Day 4–5: Countertop templater measures for slab fabrication — stone countertops take 5–10 business days to fabricate after templating. Backsplash tile installation begins during countertop fabrication wait.

Week 12: Countertop Installation and Finishes

Countertops delivered and installed. Sink plumbing trim-out completed. Under-cabinet lighting wired and installed. Electrical trim-out (outlets, switches, lighting fixtures). Backsplash tile completed and grouted. Hardware installed on cabinets.

Week 13: Final Connections and Punch List

Appliances installed and connected (dishwasher, range, refrigerator, hood). Painting touched up. Punch list walk-through with homeowner. Final city inspection. Permit closed. VGC 2-year warranty certificate issued.

Kitchen renovation services → | Get started with VGC →

Ready to start your renovation?

Vancouver General Contractors
VGC Editorial Team
✓ Licensed Contractor500+ Projects15 Years Experience

Vancouver General Contractors has completed 500+ home renovations across Metro Vancouver since 2010. Our articles are written and reviewed by licensed contractors, project managers, and renovation specialists with hands-on field experience.

1044 renovation guides published on this site.

About VGC →

Comments are closed

Renovation Contractor Serving Metro Vancouver

VGC completes kitchen, bathroom, basement, and full home renovations across the Lower Mainland. Click your city for local pricing and project information.