A full kitchen renovation in Vancouver takes 4–12 weeks from demo to final walk-through. Understanding each phase helps you plan, order materials on time, and avoid living without a kitchen longer than necessary.
Phase-by-Phase Kitchen Renovation Timeline
Phase
Duration
Demo and disposal
1–2 days
Rough plumbing (if relocating)
2–5 days
Rough electrical (new circuits)
2–4 days
City rough-in inspections
1–5 days wait
Framing / drywall repairs
2–4 days
Flooring installation
2–4 days
Cabinet delivery and installation
2–5 days
Countertop template + fabrication
7–14 days (off-site)
Countertop installation
1 day
Tile backsplash
2–4 days
Appliance installation
1–2 days
Plumbing fixtures (sink, faucet)
1 day
Electrical fixtures, switches
1 day
Touch-up and final clean
1–2 days
Total Timeline by Scope
Scope
Duration
Cosmetic (paint, hardware, fixtures)
1–2 weeks
Mid-range (new cabinets, same layout)
4–6 weeks
Full renovation (new layout)
6–10 weeks
Full renovation with custom cabinets
10–16 weeks
Critical Lead Times to Pre-Order
Custom cabinets: 8–14 weeks from order
Semi-custom cabinets: 4–8 weeks
Countertops (quartz slab): 1–2 weeks after template
Tile: stock tile 1 week, special order 3–6 weeks
Appliances: in-stock 1 week, special order 4–12 weeks
“I only put my name on companies I’d hire myself.”
— Bryan Baeumler, HGTV
15+Years in Business
✓Fixed Price Guarantee
Baeumler Approved
VGC Editorial Team
✓ Licensed Contractor500+ Projects15 Years Experience
Vancouver General Contractors has completed 500+ home renovations across Metro Vancouver since 2010. Our articles are written and reviewed by licensed contractors, project managers, and renovation specialists with hands-on field experience.